Preparation of Construction Drawings started on 20 September 2006.
The Full Scale Trial Embankment is sheduled for mid July 2007 andthe first RCC
is programmed to be placed in November 2007 with completion of the 3Mm3 of RCC
scheduled for late 2010 along with generation of the first of the 6 No 400 MW units.